Achieving the SAP C_S4PPM_2021 certification demonstrates a candidate's expertise in project management using SAP S/4HANA and can help them advance their career in project management. Certification also provides access to a global community of SAP professionals and opportunities for continued learning and professional development.
NEW QUESTION # 28
When is Bottom-up scheduling mandatory?
- A. When constraints are used
- B. When parallel phasing is used
- C. When actual time are recorded
- D. When summary tasks are used
Answer: D
NEW QUESTION # 29
You want to confirm your work hours to tasks with the cross-Application time sheet (SAP CATS). When you enter the time sheet (CAT2) your list is empty.
What could be the reason for this?
NOTE: There are 2 correct answers to this question.
- A. Your role and business partner are assigned to tasks that have the in process status
- B. Your role and business partner are assigned to task that have the created status
- C. Your user is not assigned to a business partner
- D. Your personal number is not assigned to a business partner
Answer: B,D
NEW QUESTION # 30
Which of the following object help to support automatic creation between portfolio and project management (PPM) and project system (PS)? NOTE: There are 2 correct answers to this question
- A. PS standard project
- B. PS operative project
- C. PS network
- D. PS profile
Answer: A,D
NEW QUESTION # 31
You want to confirm your work hours to tasks with the cross-Application time sheet (SAP CATS).
When you enter the time sheet (CAT2) your list is empty.
What could be the reason for this? NOTE: There are 2 correct answers to this question.
- A. Your role and business partner are assigned to tasks that have the in process status
- B. Your user is not assigned to a business partner
- C. Your personal number is not assigned to a business partner
- D. Your role and business partner are assigned to task that have the created status
Answer: A,C
NEW QUESTION # 32
No upcoming milestone are shown in the my projects SAP Fiori app.
What are the reasons for this? NOTE: There are 2 correct answers to this question
- A. Project is not released
- B. Milestone is not identified as mandatory
- C. Milestone is not identified as critical
- D. You are not defined as the project Responsible
Answer: A,D
NEW QUESTION # 33
Which of the project definition in project management must be filled before you can release a project?
- A. Project type
- B. Controlling area
- C. Responsible
- D. End date
Answer: C
NEW QUESTION # 34
What are prerequisites for using cross-Application time sheet (SAP CATS) to confirm In a project management project?
NOTE: There are 3 correct answers to this question.
- A. The planned efforts is on the task
- B. Accounting integration for this project is active
- C. The role type must allow time recording with CATS
- D. The project type must allow time recording with the CATS
Answer: B,D
NEW QUESTION # 35
You want to control the execution of subsequence phases in project management.
Which indicators must you activate in the phase type in customizing? NOTE: There are 2 correct answers to this question
- A. The approval phase indicator
- B. The complete phase when Granting Approval indicator
- C. The Release Success phase only after Approval indicator
- D. The completion required indicator
Answer: C,D
NEW QUESTION # 36
Which of the project definition in project management must be filled before you can release a project?
- A. Controlling area
- B. Responsible
- C. End date
- D. Project type
Answer: D
NEW QUESTION # 37
You have created a role in project management but the role is not displayed on the fast entry screen.
What could be the reason for this?
- A. The role has the staffing in preparation status
- B. The role has the staffing in process status
- C. The Distribution indicator is active role type customizing
- D. The flexible Assignment indicator is active in role type customizing
Answer: A
NEW QUESTION # 38
What must you configure to view portfolio item data in project management projects?
- A. Set the business content data source for portfolio management in customizing
- B. Set the portfolio management flag to active in customizing for the project type
- C. Set the project management flag to active in customizing for the linking item type
- D. Set the objects link flag to active in customizing for the project management structure
Answer: B
NEW QUESTION # 39
Which of the following are search criteria In Resource Search in Project Management?
NOTE: There are 2 correct answers to this question.
- A. plants
- B. Work centers
- C. Qualifications
- D. Organizational units
Answer: C,D
NEW QUESTION # 40
Which system behavior are enabled when a create a project with multiple phase? NOTE: There are 2 correct answers to this question.
- A. Determination of the start-dates of subsequent phases
- B. Determination of the start- and end-dates of tasks
- C. Rollup of resource requirements of tasks to phases
- D. Rollup of activity cost allocations to phases
Answer: A,B
NEW QUESTION # 41
You customer wants to involve the project manager, the staffing manager, and the candidate manager in the staffing of a project management project.
Which process requires a status change for each process step?
- A. Qualification determination
- B. Role assignment and staffing
- C. Extended staffing
- D. Staffing by authorization
Answer: C
NEW QUESTION # 42
How can you trigger a workflow for a portfolio item? NOTE: There are 2 correct answers to this question.
- A. Exceed the budget of the item
- B. Change the master data of the item
- C. Change the item status
- D. Choose the start workflow button
Answer: C,D
NEW QUESTION # 43
You want to split the financial planning values of portfolio item into two different buckets.
How do you do this?
- A. Enable the split of financial values for the item type.
* Assign the item to two bucket of the classification hierarchy
* Maintain factors to split financial planning of the item - B. Enable financial planning for multiple buckets
* Assign additional buckets in financial planning
* Maintain factors to split financial planning of the item. - C. Enable the split of financial values for the item type
* Assign the item to two bucket of the portfolio
* Maintain factors to split financial planning of the item - D. Enable process change for multiple buckets.
* Start process change to reassign the item two buckets
* Maintain factors to split financial planning of the item
Answer: A
NEW QUESTION # 44
You are in portfolio management and create a project system (PS) project from an item.
Which parts you add afterwards directly in PS? NOTE: There are 3 correct answers to this question
- A. WBS elements
- B. Network components
- C. Documents
- D. Network activities
- E. PS texts
Answer: A,B,D
NEW QUESTION # 45
......
To be eligible for the SAP C-S4PPM-2021 certification exam, candidates should have a minimum of six months of experience in SAP S/4HANA Portfolio and Project Management. They should also have a good understanding of SAP S/4HANA and should be able to use various tools and techniques to manage portfolios and projects.